In 2020, stormy weather resulted in a tree falling into the Elmwood Park pavilion, and then a major flood destroyed the park's ball fields and the damaged the Norristown Recreation center. Claims were filed with our insurance for these capital assets and money was paid out from our insurance provider to make the repairs.
There are five separate projects addressing the flood damage covered by Insurance are all currently out for bid on PennBid.net and advertised in the Times Herald. The sites will be available to potential contractors for pre-bid meetings in early February. All these projects will be under the $350,000 Responsible Contractor Ordinance (RCO) requirements, so the apprenticeship requirements of the RCO will not be required. All of the other requirements of the RCO will still be stipulated.
Below is a summary of the projects and the associated dates and times through to completion.
Rec Center
Flooring replacement contract- #PR 2021-02
- Complete floor replacement of lower basement level
- Bid opening 2/9/21 Virtual Online Bid opening @ 11:00 a.m.
- NTP 3/1/21
- Completion date 5/1/21
Planting contract- #PR 2021-01
- Drywall replacement
- Wood Door Replacement / frame/ trim
- Drop ceiling tile replacement
- Complete Repainting
- Bid opening 2/9/21 Virtual Online Bid opening @ 11:00 a.m.
- NTP 3/1/21
- Completion date 5/1/21
Sport Field Restoration Fence and infield restoration
Fencing replacement contract- #PR 2021-03
- Replacement of fencing on two baseball fields
- Bid opening 2/10/21 Virtual Online Bid opening @11:00 a.m.
- NTP 3/1/21
- Completion date 4/15/21
Baseball Infield restoration contract- #PR 2021-04
- Restoration of infield and warning tract on fields
- Bid opening 2/10/21 Virtual Online Bid opening @ 11:00 a.m.
- NTP 3/1/21
- Completion date 4/15/21
Pavilion Replacement contract- #PR 2021-05
- Demolition of existing pavilion and fireplace
- Removal of existing tree
- Construction of Prefab Wood Pavilion
- Will be an alternate for a prefab metal/ vinyl Pavilion
- Pavilion to be construction on existing slab.
- Bid opening 2/10/21 Virtual Online Bid opening @ 11:00 a.m.
- NTP 3/1/21 completion date 5/1/21